1 Scope
2 Normative references
3 Terms and definition
4 General preparations before acceptance of plant
5 Completion of erection
6 Precommissioning (mechanical completion)
7 Commissioning
8 Performance test and acceptance of plant
Annex A (informative) - List of documents to be used for
the precommissioning and commissioning phase
Annex B (informative) - Description of precommissioning
activities
Annex C (informative) - Mechanical completion certificate
Annex D (informative) - Description of commissioning
activities
Annex E (informative) - Acceptance of plant certificate
Annex F (informative) - Project-specific items
Bibliography
Annex ZA (normative) - Normative references to international
publications with their corresponding European
publications
IEC 62337:2012 defines specific phases and milestones in the commissioning of electrical, instrumentation and control systems in the process industry. By way of example, it describes activities following the 'completion-of-erection' milestone of the project and prior to the 'acceptance-of-the-plant' phase by the owner. Such activities need to be adapted for each type of process/plant concerned. This second edition cancels and replaces the first edition published in 2006. This edition constitutes a technical revision. The main changes with respect to the previous edition is: the definition of the documents mentioned in this standard is in accordance with future IEC 62708.
| Committee |
CLC/TC 65X
|
| DocumentType |
Standard
|
| PublisherName |
European Committee for Standards - Electrical
|
| Status |
Current
|
| Standards | Relationship |
| NEN EN IEC 62337 : 2012 | Identical |
| VDE 0810-37:2013-04 | Identical |
| IEC 62337:2012 | Identical |
| I.S. EN 62337:2012 | Identical |
| BS EN 62337:2012 | Identical |
| CEI EN 62337 : 2013 | Identical |
| PN EN 62337 : 2012 | Identical |
| DIN EN 62337:2013-04 | Identical |
| NBN EN 62337 : 2012 | Identical |
| NF EN 62337 : OCT 2014 | Identical |
| UNE-EN 62337:2012 | Identical |