• Shopping Cart
    There are no items in your cart
We noticed you’re not on the correct regional site. Switch to our AMERICAS site for the best experience.
Dismiss alert
Meet Inform Select. Always-on access to the Standards your organisation relies on. Explore Inform Select

ASTM E 2516 : 2006

Superseded

Superseded

A superseded Standard is one, which is fully replaced by another Standard, which is a new edition of the same Standard.

View Superseded by

Standard Classification for Cost Estimate Classification System

Available format(s)

PDF

Language(s)

English

Published date

01-10-2006

Superseded date

11-11-2014

Superseded by

ASTM E 2516 : 2011

£57.74
Excluding VAT

Committee
E 06
DocumentType
Standard
Pages
7
PublisherName
American Society for Testing and Materials
Status
Superseded
SupersededBy

1.1 This classification provides a generic classification system for cost estimates and provides guidelines for applying the classification to cost estimates.

1.2 This classification maps the phases and stages of cost estimating to a generic maturity and quality matrix, keyed to a level of project definition, that can be applied across a wide variety of industries.

1.3 The Cost Estimate Classification System has been developed in a way that:

1.3.1 provides a common understanding of the concepts involved with classifying cost estimates;

1.3.2 defines and correlates the major characteristics used in classifying cost estimates, and;

1.3.3 uses the degree of project definition as the primary characteristic used to categorize estimate classes.

ASTM E 2103/E2103M : 2013 Standard Classification for Bridge Elements—UNIFORMAT II
ASTM E 3008/E3008M : 2016 Standard Classification for Transportation Surface Elements—UNIFORMAT II

£57.74
Excluding VAT