Control systems in the process industry. Electrical and instrumentation loop check

Available format(s)

Hardcopy , PDF

Language(s)

English

Published date

31-03-2013

Superseded date

27-09-2024

Superseded by

BS EN IEC 62382:2024

£232.00
Excluding VAT

INTRODUCTION
1 Scope
2 Normative references
3 Terms, definitions and abbreviated terms
4 Order of loop check and cold commissioning in
  the project schedule
5 Loop check content
6 Loop check procedure
7 Documents and test sheets
8 Quality assurance
9 Safety aspects
Annex A (informative) - Test report for analogue
        input loop
Annex B (informative) - Test report for binary
        input loop
Annex C (informative) - Test report for analogue
        output loop
Annex D (informative) - Test report for binary
        output loop
Annex E (informative) - Test report for motors
        and variable frequency drives
Annex ZA (normative) - Normative references to
         international publications with their
         corresponding European publications

Defines the steps recommended to complete a loop check, which comprises the activities between the completion of the loop construction (including installation and point-to-point checks) and the start-up of cold commissioning.

Committee
GEL/65/3
DevelopmentNote
Supersedes 05/30140369 DC. (05/2007) Supersedes 10/30233152 DC. (03/2013)
DocumentType
Standard
Pages
24
PublisherName
British Standards Institution
Status
Superseded
SupersededBy
Supersedes

IEC 62382:2012 describes the steps recommended to complete a loop check, which comprises the activities between the completion of the loop construction (including installation and point-to-point checks) and the start-up of cold commissioning. This standard is applicable for the construction of new plants and for expansion/retrofits (i.e. revamping) of E&I installations in existing plants (including PLC, BAS, DCS, panel-mounted and field instrumentation). This second edition cancels and replaces the first edition published in 2006 and constitutes a technical revision. The main changes with respect to the previous edition are: The definition of the documents mentioned in the standards is in accordance with IEC 62708: Documents for Electrical and Instrumentation Projects in the Process Industry. Subclause 6.3 has been revised.

Standards Relationship
DIN EN 62382 : 2014 Identical
IEC 62382:2012 Identical
NBN EN 62382 : 2013 Identical
I.S. EN 62382:2013 Identical
NF EN 62382 : 2014 Identical
EN 62382:2013 Identical
IEC 60898-1:2015/COR1:2015 Identical
UNE-EN 62382:2013 Equivalent

IEC 62708:2015 Documents kinds for electrical and instrumentation projects in the process industry
EN 62424:2016 Representation of process control engineering - Requests in P&I diagrams and data exchange between P&ID tools and PCE-CAE tools
EN 62337:2012 Commissioning of electrical, instrumentation and control systems in the process industry - Specific phases and milestones
IEC 62337:2012 Commissioning of electrical, instrumentation and control systems in the process industry - Specific phases and milestones
IEC 62424:2016 Representation of process control engineering - Requests in P&I diagrams and data exchange between P&ID tools and PCE-CAE tools

£232.00
Excluding VAT